Project Scope

This was a two-stage project over 2013 and 2014. MCA Engineering came up with a proposal to lower cans in an Ore Pass using a MCA designed Chain Jack System.

This system enabled Cadia to complete the schedule 2 months in earlier than previous ore passes.

The project was a major success with great feedback from the clients. We intend to use the Chain Jack System for many other projects in the future.

Project Downloads
Work With Us

MCA offer a wide range of services including concept design studies, detailed design, fabrication and construction. For more information, please contact us to discuss how we can assist you with your next project.

Overview

Year: 2013 – 2014

Client, Project, Location:
Newcrest, Cadia Ore Passes, Cadia East Mine, Orange NSW

Contact Type: Fixed

Role: Subcontract

Contract Value: $2.8 million


Our services

Gallery